ONE-Dyas has already received all required permits for project N05-A from the Dutch government in 2022. The permit to install a cable between the platform and Riffgat wind farm was also issued by NLWKN (Lower Saxony Department of Water, Coastal and Nature Conservation) in 2022.
In 2024, the State Council’s preliminary injunction judge rejected the objections of opponents and ruled that ONE-Dyas could go ahead with the offshore work. No appeal is possible against this decision of the Council of State and therefore ONE-Dyas could immediately proceed with its planned activities in the North Sea. The power cable construction licence was temporarily suspended due to new requirements in the licensing process. At the end of August, ONE-Dyas delivered all required documents and the NLWKN has now started the process for granting the amended licence. The cable link is expected to be completed in spring 2025.