Installation work North Sea

In the summer of 2024, production platform N05-A was installed in the North Sea, after which the pipeline was laid and successfully connected to the existing infrastructure of Noordgastransport NGT. Since 2025, natural gas from the first production well of the N05-A field in the Dutch sector of the North Sea is being produced.

Below is the broad outline of the planning from transport to production. This planning depends, among other things, on weather conditions.

Third production well N05-A
July 2026

ONE-Dyas has started gas production from the third production well on the N05-A platform in the North Sea. This increases N05-A’s production to 2 billion cubic metres per year.

Second production well N05-A
April 2026

ONE-Dyas has started gas production from the second production well on the N05-A platform in the North Sea. This increases N05-A’s production to 1 billion cubic metres per year.

Mobile drilling rig
From December 2025

The drilling is fully electric, using green electricity from the nearby German wind farm Riffgat. As a result of electrification, emissions during drilling are near-zero. A temporary mobile drilling platform will be installed on site for the drilling operation and will be removed again once the work has been completed. The production from the German wells is expected to start in the first half of 2026.

Installation of power cable
Fall 2025

The platform will be the first offshore gas treatment platform in the Dutch North Sea to run on offshore wind energy. For this purpose, a cable has been laid to the nearby German Riffgat wind farm. This connection results in near-zero emissions during the drilling of wells and the production of natural gas.

Start test phase
Winter 2024/2025

In March 2025, the test phase of production from the N05-A platform began, with natural gas being produced. The natural gas is transported to the mainland via the new short pipeline and the existing NGT pipeline. Until the cable can be installed, gas generators are temporarily being used.

Pipeline installation
October 2024

Construction of the gas pipeline is under way. A short, new natural gas pipeline of about 15 kilometres will be laid from production platform N05-A to the existing natural gas pipeline network of Noordgastransport (NGT). The temporary works are partly visible from the shore.

Due to poor weather conditions, the work has not yet been completed. It is expected that the installation ship will be able to leave in mid-February.

Mobile drilling rig
from September 2024

In autumn, ONE-Dyas drilled the first well from which natural gas can be produced from field N05-A in the Dutch part of the North Sea. Before drilling, a mobile drilling rig was temporarily at the project site. Now that the first well has been drilled, the mobile drilling platform has left again. The production platform N05-A will be used to produce the natural gas.

Installation production platform N05-A
End of July/Early August 2024

The N05-A production platform is installed in the North Sea at the beginning of August. The installation did take place using a crane vessel that runs on liquefied natural gas instead of the commonly used diesel. This minimises emissions during installation.